To pass inspection for sale this waterfront property needed a new retaining wall installed to relieve the pressure off of the existing wall which had started to fail. We dug back and laser leveled the hand stacked blocks, a diversion drain system was also put in. The process took less than a week, even under tight fitting site conditions.

Location: Mossyrock

Size: 35′ long

Build Date: January 2018

Designed By: Luke Moerke of Exodus Engineering